Mammoet key link in The Dubai Mall extension logistics

Mammoet’s LR1750 crawler crane used in lifting and installation of 16 steel girders form the base of The Dubai Mall’s Fountain View Link-Bridge.
The project constrains meant the crane needed to have a minimal footprint and low ground bearing pressure.
The project constrains meant the crane needed to have a minimal footprint and low ground bearing pressure.

Share

SEE ALSO: REPORT: Breakbulk logistics a bright spot in 2017?

SEE ALSO: Interview: Breakbulk specialists AAL

SEE ALSO: Breakbulk Middle East opens in Abu Dhabi

Mammoet were contracted by Eversendai to assist in the erection of the new bridge which will connect the existing mall to a new section. The Fountain view Link-Bridge will be home to retail outlets and provide a walk way to further parking.

The project constrains meant the crane needed to have a minimal footprint and low ground bearing pressure. Mammoet’s LR1750 crawler crane was the only available crane in the UAE that complied with all technical requirements.

It installed the girders, weighing between 83 and 172 metric tons, in two sections.

RELATED: Project logistics expert Mammoet expands in Middle East

RELATED: What to expect at Breakbulk Middle East 2018

The lifts were carried out on Sheikh Mohammed bin Rashid Boulevard, the main road that runs around Dubai Mall. With only two out of six lanes closed to minimize disruption to traffic, the crane had to manoeuvre in a tight space.

And there was another engineering challenge: water pipes underneath the area of operation supply Dubai Mall and the whole of Down Town Dubai.

To avoid damaging them, it was imperative that the crane kept within the ground bearing pressure tolerance. Careful engineering calculations were made for the lifts to ensure that the LR1750 could lift the girders and manoeuvre in to place without nearing traffic, or going over the ground bearing pressure limit.

Mammoet installed the first set of girders on the Fountain View side of the road. The whole operation was then moved to the mall side of the road where the other halves of the girders were installed, ready for connection in the middle.